Project Background

The District recently discovered that several manholes and pipes in 9400 South that have suffered extreme hydrogen sulfide damage.  The pipe needs to be lined and portions relayed.

Project Scope

Line/relay the corroded 18-inch concrete pipe.

Project Purpose

Repair a severely damaged pipe.

 

Contractor:

TBD

Project Timetable

Bid Date
Award Date
Construction Begin Date
Substantial Completion
Completion Date

April 2014
April 2014
April 2014
June 2014
July 2014

Project Status
The design is complete and the project is out to bid.